Skip to content

Backlogs · Planning assumption

Net backlog burn rate calculator

Find how much backlog can be reduced each day. The formula is daily completion capacity − daily arrivals.

Backlogs · Planning assumption

Try the calculator

Find how much backlog can be reduced each day.

Use your active project

Upload data or load a sample in the workspace, then return here using the Calculation Library link. The project stays in memory during site navigation; a full refresh clears it. Save your private project before closing or refreshing.

ReferenceFormula

daily completion capacity − daily arrivals

Calculator inputs

Your result

Daily backlog reductionCalculated
200 contacts/day

Calculator baselines and manual scenarios do not change your planning project. Related workflow: Staffing Strategy. The active project remains in browser memory during client navigation; full refresh clears it. Calculator edits stay in this page’s memory; only favourite calculator IDs are remembered in this browser. Downloads are created on your device.

How it’s calculated

Net backlog burn rate = daily completion capacity − daily arrivals

Inputs: completion capacity (contacts/day); arrivals (contacts/day). Use consistent definitions for every input.

This is a planning estimate: an aggregate figure built on assumptions that should be checked against how your operation actually runs.

Worked example

These are the calculator’s example inputs; the results below are produced by the same function that runs the calculator above.

Example inputs
InputValueUnit
Completion capacity1200contacts/day
Arrivals1000contacts/day

Result

Daily backlog reduction
200 contacts/day

When this is wrong

  • Negative means backlog grows.
  • Assumes stable daily demand and completion capacity.

Definitions: metric glossary. How LoughPoint applies these methods to a full plan: methodology. All 50 calculators.