Ending backlog calculator

Estimate the work left after arrivals and completions. The formula is max(0, opening backlog + arrivals − completions).

Backlogs · Identity

Try the calculator

Estimate the work left after arrivals and completions.

Use your active project

Upload data or load a sample in the workspace, then return here using the Calculation Library link. The project stays in memory during site navigation; a full refresh clears it. Save your private project before closing or refreshing.

ReferenceFormula

max(0, opening backlog + arrivals − completions)

Calculator inputs

Your result

Ending backlogCalculated
400 contacts

Calculator baselines and manual scenarios do not change your planning project. Related workflow: Staffing Strategy. The active project remains in browser memory during client navigation; full refresh clears it. Calculator edits stay in this page’s memory; only favourite calculator IDs are remembered in this browser. Downloads are created on your device.

How it’s calculated

Ending backlog = max(0, opening backlog + arrivals − completions)

Inputs: opening backlog (contacts); arrivals in period (contacts); completions in period (contacts). Use consistent definitions for every input.

This is an identity: arithmetic from defined inputs. The answer is exact, so what matters is that every input uses the same definitions, scope and period.

Worked example

These are the calculator’s example inputs; the results below are produced by the same function that runs the calculator above.

Example inputs
InputValueUnit
Opening backlog500contacts
Arrivals in period1000contacts
Completions in period1100contacts

Result

Ending backlog
400 contacts

When this is wrong

  • Use the same work unit and period.
  • Transfers, reopened work and cancellations need separate reconciliation.

Definitions: metric glossary. How LoughPoint applies these methods to a full plan: methodology. All 50 calculators.