Staffing & shrinkage · Planning assumption
Call centre staffing calculator: how many FTE do you need?
To estimate the full-time equivalents (FTE) a contact centre needs for a period, convert contacts into handling hours, allow for occupancy and shrinkage, then divide by the paid hours one FTE works in that period. This calculator shows each step so you can check it.
Staffing & shrinkage · Planning assumption
Try the calculator
Trace demand through workload, occupancy and shrinkage to roster size.
Use your active project
Upload data or load a sample in the workspace, then return here using the Calculation Library link. The project stays in memory during site navigation; a full refresh clears it. Save your private project before closing or refreshing.
ReferenceFormula
contacts × AHT ÷ [3,600 × concurrency × hours/FTE × occupancy × (1 − shrinkage)]
Calculator inputs
Your result
- Handling workloadCalculated
- 833.3333 hours
- Available agent time neededCalculated
- 980.3922 hours
- Paid roster time neededCalculated
- 1,400.5602 hours
- Roster requirementCalculated
- 8.7535 FTE
- Whole full-time peopleCalculated
- 9 people
Calculator baselines and manual scenarios do not change your planning project. Related workflow: Staffing Strategy. The active project remains in browser memory during client navigation; full refresh clears it. Calculator edits stay in this page’s memory; only favourite calculator IDs are remembered in this browser. Downloads are created on your device.
How it’s calculated
Demand to roster FTE = contacts × AHT ÷ [3,600 × concurrency × hours/FTE × occupancy × (1 − shrinkage)]
Handling workload = contacts × AHT ÷ 3,600 (divided by effective concurrency for chat). Available agent time = workload ÷ occupancy. Paid roster time = available time ÷ (1 − shrinkage). Roster FTE = paid roster time ÷ paid hours per FTE.
Use demand and paid hours for the same period: a month of contacts with the paid hours one FTE works in that month, or a week with weekly hours. The result is FTE, not people. Part-time contracts mean more people than FTE; convert with the FTE to headcount calculator.
This is a workload (aggregate) method. It suits monthly and annual planning, budgets and hiring plans, but it does not know when contacts arrive during the day.
For live voice and chat, the staffing you actually need is driven by the busiest intervals. Size those with the Erlang C calculator and add shrinkage. Fitting real shifts to that pattern usually takes more paid hours than the aggregate workload figure, because shifts cannot follow demand exactly.
Worked example
These are the calculator’s example inputs; the results below are produced by the same function that runs the calculator above.
| Input | Value | Unit |
|---|---|---|
| Contacts | 10000 | contacts |
| Average handling time | 300 | seconds/contact |
| Paid hours per FTE in this period | 160 | hours/FTE |
| Occupancy | 85 | % |
| Shrinkage | 30 | % |
| Effective concurrency (1 for single-contact work) | 1 | simultaneous contacts |
Result
- Handling workload
- 833.33 hours
- Available agent time needed
- 980.39 hours
- Paid roster time needed
- 1,400.56 hours
- Roster requirement
- 8.75 FTE
- Whole full-time people
- 9 people
When this is wrong
- Occupancy is a planning assumption here. Setting it high makes the plan look cheaper but may be unachievable for a small team with peaky demand, where queueing maths gives lower occupancy for the same service.
- Shrinkage must be measured on the same basis as the paid hours. Do not remove breaks from paid hours and then count them again in shrinkage.
- New-starter training, attrition and ramp-up are not included. Use the attrition and hiring calculator, and plan training time separately.
Related calculators
- Erlang C calculatorSize available interval agents for service and occupancy constraints.
- ShrinkageConvert an available requirement into a scheduled requirement.
- Headcount to FTENormalise part-time contracts into full-time equivalents.
- FTE to part-time headcountTranslate FTE into people at a stated contract length.
- FTE gapCompare the requirement with funded or available roster FTE.
- Workload-based net FTEFind available FTE before allowing for shrinkage.
Definitions: metric glossary. How LoughPoint applies these methods to a full plan: methodology. All 50 calculators.